Installation Instructions

brick veneer

Design No. S4

Brick Veneer Walls

  1. Roll out AIR-CELL® horizontally and fix to outside of internal wall frame, working from the bottom up.
  2. Allow 50mm overlap between top and bottom layers and tape 48mm reinforced foil tape.
  3. Cut AIR-CELL® carefully around doors, windows and other openings, so that it neatly abuts to frames
  4. Penetrations for wall ties or services should be neatly cut to minimize gaps.

 

These instructions are guidelines only and should be interpreted with consideration for the specific building design. This installation of AIR-CELL® should be in conformance with the applicable clauses for AS 3999 and AS/NZS 4200.2 unless otherwise specified.

AIR-CELL® can be damaged by intense heat above 135°C and contact with sparks and flame from blow torches, welders, cutting tools, etc. must be avoided.

The installer must make due provision for safety when installing AIR-CELL® in any application

 

Handling and Storage
AIR-CELL® Insulation products must be transported in its protective packaging and kept clean and dry. Standing rolls on end reduces risk of damage should moisture be present in the packaging. Surfaces must be kept free of contaminants such as dust and greese, and must not be stored with foil surfaces in contact with alkaline materials i.e. wet cement, lime, etc.