Design No. C2C

 

Concrete Roofs

  1. Attach mounting system of choice (battens, furring channels, ceiling mountings, etc.) to the underside of the concrete considering ceiling system to be installed, if any.
  2. Fix AIR-CELL® to the underside of the mounting system leaving a 50mm minimum overlap.
  3. Tape joins and penetrations with min 48mm wide reinforced foil tape.

Note: Where a ceiling lining is to be installed allow a minimum of 16mm air space between the lining and the AIR-CELL®

These instructions are guidelines only and should be interpreted with consideration for the specific building design. This installation of AIR-CELL® should be in conformance with the applicable clauses from AS 3999 and AS/NZS 4200.2 unless otherwise specified.

AIR-CELL® can be damaged by intense heat above 135˚ C and contact with sparks and flame from blow torches, welders, cutting tools, etc. must be avoided.

The installer must make due provision for safety when installing AIR-CELL® in any application

 

Handling and Storage
AIR-CELL® Insulation products must be transported in its protective packaging and kept clean and dry. Standing rolls on end reduces risk of damage should moisture be present in the packaging. Surfaces must be kept free of contaminants such as dust and grease, and must not be stored with foil surfaces in contact with alkaline materials i.e. wet cement, lime, etc.