Double Brick Walls

Double Bricked Walls

Design No. S5

 

  1. Lay outer leaf or brickwork with wall ties in place.
  2. Clip AIR-CELL® Spacer Biscuit onto every second wall tie and push against brickwork.
  3. Roll out AIR-CELL® horizontally (anti-glare facing installer) and offer up to the wall.
  4. Cut a slit for each wall tie to penetrate the AIR-CELL®.
  5. Push the AIR-CELL® over the wall ties until it is against the Spacer Biscuits.
  6. Allow a 50mm overlap at joins with the upper layer overlapping on the outside of the lower, and tape with a 48mm wide reinforced foil tape.

+ Download Installation Brochure

These instructions are guidelines only and should be interpreted with consideration for the specific building design. This installation of AIR-CELL® should be in conformance with the applicable clauses from AS 3999 and AS/NZS 4200.2 unless otherwise specified.

AIR-CELL® can be damaged by intense heat above 135˚ C and contact with sparks and flame from blow torches, welders, cutting tools, etc. must be avoided.

The installer must make due provision for safety when installing AIR-CELL® in any application.

 

 

Handling and Storage
AIR-CELL® Insulation products must be transported in its protective packaging and kept clean and dry. Standing rolls on end reduces risk of damage should moisture be present in the packaging. Surfaces must be kept free of contaminants such as dust and grease, and must not be stored with foil surfaces in contact with alkaline materials i.e. wet cement, lime, etc.


 